  • Rehabilitation of 10″ and 4″ pipelines on Ascencion Island

    2023

    The scope of project was rehabilitation of product pipeline serving fuel to the airport and power plant including repair of pipeline support system.

  • Replacement of the additive unit on Ascension Island

    2023

    The project included engineering, production, delivery and commissioning of the additive dosing unit for JET-A1, tank gauging for the additive tanks and a simple roof to protect the technology.

  • Modernisation of LPG tanktruck and railway loading posts at SCDP depot Bonaberi, Cameroon

    2022

    Evaluation of existing situation, design, production, installation and putting in service of new metering lines to fit into existing site layout. Including automatic loading control by flow computers and terminal administration system TAMAS.

  • Instalation of control system TAMAS V0 + Info Panels, Gabon

    2022

    Instalation of control system TAMAS V0 + Info Panels for truck loading queue traffic management for SGEPP Gabon Libreville

  • Metering Station for strategic depot in Yaoundé, Cameroon

    2022

    Engineering, Manufacturing, Commissioning of Custody Transfer Metering Station for railway/truck unloading of fuels at Nsam terminal in capital city of Cameroon

  • Grounding Testers in Gabon

    2022

    Delivery and Commissioning of Truck Loading Grounding tester for SGEPP Gabon.

  • Custody Transfer Metering SKIDs for NNPC Nigeria

    2022

    Custody Transfer Metering SKIDs for NNPC Nigeria Engineering/Design/Manufacturing/Delivery/Installation/Commisioning of metering SKIDs up to 24" on crude oil/products pipelines on the pipelines network in Nigeria.

  • Unloading/Loading SKID for NATO airbase at Liwatom Estonia

    2022

    Unloading/Loading SKID for NATO airbase at Liwatom Estonia.

  • Technology for Bangladesh DHAKA airport

    2022

    Technology for Bangladesh DHAKA airport new fuel terminal Delivery of loading/unloading SKIDs, SCADA & Leak Detection System & ESD for pipeline, Pump Station, Valves etc.

  • Upgrade and unification of telemetry system VaK Mlada Boleslav

    2022

    Unification of potable and waste water telemetry system into a central control system for potable water distribution and waste water processing including upgrade to latest SCADA version.

  • Filters / water separators and tanks edge protection on Falkland Islands

    2022

    Modernisation of Filters / water separators for aviation fuels and installation of tanks edge protection on fuel storage tanks for improvement of staff safety.

  • Loading the BA100 SuperPlus into the tank truck in PARAMO

    2022

    Modifications of pipelines in front of and on the loading terminal. Installation of a new metering SKID approved for custody transfer. Extension of additive pipes with electric heating and insulation. Installation of a new EVAPlus and AccuPlus additive unit with five inputs. Installation of a new loading arm for the bottom filling of tank trucks and vapour extraction. Modifications of the control system.

  • System for Centralised Information System of Sudanese Ministry of Petroleum (SPC)

    2021

    DMSP (Depo Monitoring System Project) centralise all technology data from all depots and in HQ there is full control of actual inventories in Sudan. DMSP project includes also completely new HW like dual redundant SCADA servers, workstations, large screen monitors, communication converters, SW licences and mobile devices.

  • Water supply system Damnice

    2021

    Control and telemetry system on water distribution objects and integration to existing central SCADA system.

  • Upgrade and unification of central telemetry system VAS Znojmo

    2021
  • Water supply system Jedovnicko

    2021

    Control and telemetry system on water distribution objects and integration to existing central SCADA system.

  • Wastewater pumping station in Ostrava

    2021

    Modernisation of control system and integration to existing central SCADA system at 5 wastewater pumping stations.

  • Modernisation of fire fighting system at UK military airbase on Ascension island

    2021

    Diesel handling system for fueling of fire water pumps and commisioning of the fire fighting system.

  • Water supply system Božice

    2020

    Control and telemetry system on water distribution objects and integration to existing central SCADA system.

  • Rehabilitation of waste water plant Bakov nad Jizerou

    2020

    Complex reconstruction of the control system.

  • New tanktruck loading terminal Čepro Loukov

    2020

    EPC construction of new terminal with 16 arms at 4 loading places for all kinds of fuel with biofuels blending and additive dosing. Project included as well new manifold, piping, extension of control system TAMAS, CCTV, switch room, cabling, security system, fire detection. New fire fighting system with new fire water tank 500 m3 .

  • Modernisation of tank truck and railway terminal at Bessengue and Nsam – Phase I., Cameroun

    2020

    EPC delivery of new technology, control and administration system for loading of fuels (gasoiline, diesel, kerosene, JET-A1) to tanktrucks and railcars and unloading of the product from tanktruck and railcars. The first phase includes design and delivery of the metering equipment.

  • Energetika Třinec – replacement of old turbo-compressor

    2019

    The project scope covered design, removal of existing, install new and commission new electrical Turbo-Compressor with significant energy reductions increased efficiency leading to “Life Cycle” operational benefits. The project was run under a ‘Turn-Key’ basis.

  • Reconstruction of water treatment plant Hrdibořice

    2019

    Modernisation and extension of control system.

  • Reconstruction of control system at water source Důlňák

    2019

    Delivery and commissioning of new control room system ClearScada SCX6.

  • Optimisation of phosphorus coagulant dosing at waste water plant Blansko

    2019

    Wireless data transmition between control PLC, sensor and dosing unit including modification of control system.

  • Modernisation of control system at waste water plant Blansko

    2019

    Delivery and commissioning of new control room system ClearScadaSCX6 and modification of existing process control system.

  • Driver for SMS communication to security system in Hodonín

    2019

    Development, testing and commissioning of special driver for SMS communication between security system and control room system ClearScada SCX6.

  • Detail design of control room modernisation at waste water plant Ostrava

    2019

    Elaboration of detail design for project "Modernisation of control room at WW plant Ostrava". Includes SCADA part of control system incl. HW.

  • Pipeline additive dosing unit for Slovnaft, Slovakia

    2019

    EPC project - design, production, delivery and start-up of container - based unit for dosing of additive (drag reducing agent) into high pressure product pipelines. Including integration to existing pipeline control system.

  • Paramo – modernisation of vapour recovery system

    2019

    EPC construction of vapour recovery unit (VRU). Installation of VRU with capacity 380 Nm3 /h to fulfill emission limit 150 mg/Nm3 . Demolition of existing VRU, partial rehabilitation of piping system, delivery and installation new vapour low profile arm for unloading of railcars. Complete ground and construction works, electrical installations, lightning protection and grounding, illumination and field instrumentation.

  • Paramo – modernisation of additive dosing

    2019

    EPC construction of additivation technology for diesel and gasoline on the loading rack for tank truck filling. Underground tank with double wall, total capacity 100 m3 in 10 sections. Construction of new pumping station for unloading and delivery of additives, stainless steel piping with electrical heating and insulation. Installation of 5 new additive injectors AccuPlus including EVA Plus, each with 5 inlets, new loading place for bottom loading.

  • New tank truck terminal and product pipeline for Jet-A1 product at Vaclav Havel International Airport Prague

    2019

    Vaclav Havel International Airport Prague is the biggest airport in Czech Republic with more than 15 million passengers per year. In this project was built completely new facility for tanktrucks for delivery of JET-A1 fuel to aircrafts. Our scope included technology for JET-A1 loading to tanktrucks (metering runs - SKIDs with flow computers Accuload IV incl. metrology approval according to MID, new control system, cabling and field instruments and additive dosing (conductivity improver) at terminal inlet. The scope included also complete design documentation.

  • Construction of new JET-A1 storage tank at Vaclav Havel Airport Prague

    2019

    Construction of storage tank with volume 5000 m3 for aviation fuel JET-A1. The works included also new related piping, field instruments, extension of control system, CCTV, fire detection and fire fighting EPS, security system, fencing, new tank for fire water, oily water separator, demolish of old fire water tank and diesel handling storage technology.

  • Technology for tank truck loading and additive dosing at new Beijing – Daxing airport, China

    2019

    Design and delivery of technology for JET-A1 fuel delivery to the airport tank trucks and technology for additive dosing (conductivity improver) at JET-A1 fuel terminal inlet.

  • Reconstruction of sediment treatment at waste water plant Blansko

    2018

    Modification and extension of process control system.

  • Modernisation of water treatment plant Landštejn

    2018

    Modernisation of control room system HW and SW - new modern system ClearScada SCX6.

  • Modernisation of waste water plant Polička

    2018

    Komplex delivery and commissioning of control room and integration to existing central telemetry system.

  • Improvement of cyber security of control room Středočeské vodárny

    2018

    Execution of arrangements for cyber security improvement and water distribution telemetry system and control room.

  • Driver for communication with sensors over IoT for VAS Znojmo

    2018

    Development, testing and commissioning of special driver for communication between existing control room system ClearScada SCX6 and sensors over IoT (Internet of Things).

  • Capacity extension at water collection area Lednice

    2018

    Control and monitoring of new built wells and integration to existing water treatment plant process control system.

  • Ships bunkering terminal for Alexela Slovag, Norway

    2018

    Design, fabrication, commissioning of skids for delivery of fuel (diesel) to ships. The skids are certified according to MID and enable fast bunkering of marine ships.

  • Pipeline additive dosing units for Cepro

    2018

    Design, production, start-up of mobile units for dosing of additive - drag reducing agent into high pressure product pipeline.

  • Construction of liquid storage in a new car production plant, Slovakia

    2018

    Construction of a warehouse for operating fluids and piping into the assembly hall of the new Jaguar Land Rover production plant. The scope included construction of a liquid storage facility with 9 tanks for products and 1 tank for slop. The stored and pumped substances are: petrol, diesel arctic, diesel summer, brake fluid, screen wash, refrigerant R134A, AD BLUE, antifreeze, refrigerant R1234YF.

  • Design for JET-A1 railway unloading for Chegdu airport, China

    2018

    Design documentation of technology and control system for top unloading of JET-A1 from railcars for newly constructed airport Chengdu Tianfu.

  • Telemetry at object Aqualand Moravia

    2017

    Complex provision of telemetry point and data transmition to central water distribution control room of operator VaK Břeclav.

  • Sediment treatment at waste water plant Svitavy

    2017

    Extension and modification of process control system.

  • Reconstruction of MV swith room at waste water plant Ostrava

    2017

    Modification and extension of process control system.

  • Operation security of water authority Svitavy

    2017

    Evaluation of operational and cyber security of selected objects and central control room for water distribution.

  • Improvement of operation security at control room VHOS Moravská Třebová

    2017

    Evaluation of operational and cyber security of selected water distribution objects and central control room.

  • Drivers for communication with 3rd party systems at waste water plant Vrapice

    2017

    Development, testing and commissiong of drivers for communication between control room system ClearScada SCX6 and non-standard 3rd party systems.

  • Metering lines for biofuels blending at MOL terminals, Hungary

    2017

    This project included design, delivery, commissioning and metrological certification of metering skids for FAME with maxiumum capacity of 45 m3 /h. The skids were installed in different MOL terminals.

  • Loading equipment for road and marine terminal BMF Burgas, Bulgaria

    2017

    The scope included design, delivery, commissioning and metrological certification of metering lines for unloading and loading of trucks and for unloading of ships, bio-blending equipment, valves and other accessories, additive dosing system, grounding monitors, bottom loading arms and level gauging system.

  • Extension of liquid cargo terminal in Koper, Slovenia

    2017

    Engineering, production, delivery and start-up of technology for measuring of light products including JET-A1 loaded to tanktrucks and railcars. Metering lines in a form of skids, independent density measurement, additive dosing and colouring system, loading arms. System for automation and administration of the terminal - TAMAS.

  • Construction of fuel terminal Dongguan, China

    2017

    Based on previously executed design, production, delivery and start-up of technology for tanktrucks loading and complete low-voltage part, including control and administration system TAMAS.

  • Modernisation of solar power system, Sudan

    2017

    Upgrade of solar power system at Fula to Khartoum heavy crude export pipeline. The scope included delivery and configuration of units (RTUs) for control of accumulator charging from solar panels.

  • Sediment treatment at waste water plant Velká Bíteš

    2016

    Extension and modification of process control system.

  • Reconstruction of water treatment plant Hrdibořice

    2016

    Modification of process control system during reconstruction of aeration part.

  • Modernisation and reconstruction of waste water plant Zaječí

    2016

    Komplex execution of following parts: low voltage, field instrumentation, process control, control room.

  • Improvement of operation security of water distribution control room Mladá Boleslav

    2016

    Delivery and commissioning of redundant part for central control room in Hot - Standby mode.

  • Modernisation of terminal OKTAN Dětmarovice

    2016

    Modernisation of technology for storace of liquid fuels, unloading from railcars and loading to tanktrucks including biofuels blending.

  • INA, Modernisation of tanktruck terminal in Rijeka refinery, Croatia

    2016

    Engineering, production, delivery and start-up of technology for measuring of light and heavy products loaded to tanktrucks. Metering lines in a form of skids, independent density measurement, extension of additive dosing system, tanktrucks weight scales, loading arms. System for automation and administration of the terminal - TAMAS.

  • Port Sudan strategic terminal project, Sudan

    2016

    Design, production, delivery and start-up of high capacity flow metering skids, tank gauging system, control system (PLC, ESD, SCADA, TAMAS), fire detection and control of firefighting system.

  • PRECHEZA a.s. Přerov – Strengthening expedition of sulphuric acid

    2015

    The supply and installation of two vertical storage tanks (capacity of each 50 m3), pipeline, valves, pump and steel structure.
    Czech Republic / 2014 - 2015

  • Control room at waste water plant Rakvice

    2015

    Control room for management of waste water plant incl. integration into superordinate system of operator VaK Břeclav.

  • Reconstruction of OKTAN Kežmarok unloading and loading terminal, Slovakia

    2015

    Modernization of flow measuring system according to MID requirements, equipment for biofuels blending, additive dosing system, automation and dispatching system.

  • Pipeline SCADA upgrade project, Sudan

    2015

    Delivery of SCADA system for monitoring of 2 product pipelines with total legth over 1500 km including 12 pumping stations, 10 block valve stations and 3 cathodic protection stations.

  • Construction of JET fuel storage in Lielvarde airfield, Latvia

    2015

    The contract for NSPA: Construction of new terminal JET-A1 with 2 vertical storage tanks, one place for tank trucks unloading, two SKIDS for tank trucks loading, additivation system, instrumentation, control and administration system TAMAS.

  • Mondi Štětí a.s. – Green Liquor Handling Upgrade

    2014

    The construction of three different types of aboveground storage tanks (capacity 1500 m3 , 200 m3 and 140 m3 ) and manufacturing and supply tank 0.4 m3 . All tanks completely made of stainless steel. Including complete insulation and sheathing.

  • Private APN network for water authority Mladá Boleslav

    2014

    Start-up of APN network for secure communication between water distribution and waste water objects and central control room over GSM/GPRS network.

  • Modernisation of waste water plant Mnichovo Hradiště

    2014

    Connection of waste water plant into existing central waste water control room Mladá Boleslav.

  • Vendys&V, Custody transfer measurement and additive dosingin the new part of terminal Ceska Lipa

    2014

    Design, delivery and start-up of technology and control system for tanktruck loading measurement in the extended part of the terminal. As well as existing part, also the new equipment was delivered in form of skid and approved according to MID.

  • Additive dosing at Petrochina Shilou terminal, China

    2014

    Delivery and start-up of additive dosing system for tanktruck loading terminal for 9 loading lines. Complete additive dosing technology system: unloading, storage, delivery, system integration.

  • Detail design for Dongguan terminal, China

    2014

    Detail Design Documentation Package for newly built Petrochina terminal in Dongguan. Includes technology for tanktruck loading and control system for the entire tankfarm with planned capacity 400.000 m3 . Dongguan is first Chinese terminal designed according to European conventions.

  • TECHNOEXPORT, a.s. Praha – Delivery of the SKIDs and control system TAMAS – DUKAN Refinery, Iraq

    2014

    Design, fabrication and start-up assistance for ten pieces measuring SKIDs and loading arms for loading tank truck, custody transfer of different products. Seven pieces for light products a three pieces for heavy products with heating and insulation.

  • Mondi Štětí a.s. – Storage of light fuel oil 1300 m3

    2013

    The construction of new reservoir for light fuel oil (capacity 1300m3), including unloading system, pipelines and new system of measurement and control.

  • Lučební závody Draslovka a.s. Kolín

    2013

    Construction of a new warehouse ammonia. New building storage with three cylindrical tanks with a capacity of 95 m3 each, slop tank for unloading rail cisterns, bottom unloading arm, new pipelines, the new control room, ammonia leak detection, sprinkler system, new MaR and control system.

  • Heating plant PGE Kielce

    2013

    Design, delivery and recovery of electrical and automation control of technology at heating plant PGE Kielce.
    (This project was implemented by subsidiary AUTEL, a.s.)

  • WWTP Velké Meziříčí, Czech Republic

    2013

    Reconstruction of the wastewater treatment plant (WWTP) in Velke Mezirici, CZ.

  • Vodovody a kanalizace Mladá Boleslav – Upgrade to the SCX 6

    2013

    Vodovody a kanalizace Mladá Boleslav (CZ) - Upgrade to the SCX 6. Licence and software work in connection with the transition to the SCX 6.

  • VaS Žďár nad Sázavou – TSWM/LP Stations

    2013

    VaS Žďár nad Sázavou - delivery of TSWM/LP stations.

  • OVAK – Upgrade to the SCX 6, Czech Republic

    2013

    Ostravské vodárny a kanalizace (OVAK, Czech Republic) - Upgrade to the SCX 6 for central dispatching of drinking water lines. Licence and software work in connection with the transition to the SCX 6. TSWM/LP stations.

  • Jihočeský vodárenský svaz – TSWM/LP Stations

    2013

    Jihočeský vodárenský svaz - delivery of TSWM/LP stations.

  • Delivery of vapor recovery unit for ENI, Italy

    2013

    Fabrication of 400 m3 /h vapor recovery unit (cleaning of gasoline vapors) for marine loading terminal Livorno, EPC Jordan Technologies.

  • Custody metering SKIDs for Gasoline/Diesel/LPG Storage in harbour Port Sudan

    2013

    Metering skids for Port Sudan storage depot for Loading/Unloading liquid products. Skids with size upto 16" are designated for custody transfer.

  • Water Treatment Plant Kroměříž – Reconstruction and Upgrade to the SCX 6

    2012

    Reconstruction of water treatment plant in Kroměříž (CZ), upgrade to the SCX 6, licenses, software and editing work in the visualization of the central dispatching of the Waterworks and Sewerage Kroměříž.

  • Vodovody a kanalizace Mladá Boleslav, CZ

    2012

    Vodovody a kanalizace Mladá Boleslav - delivery of TSWM/LP stations; creation and operation of the APN network,; license and software work related to the transition to SCX6 - participation of the client.

  • Vak Prostějov – Upgrade to the SCX 6

    2012

    Vodovody a kanalizace Prostějov (CZ) - Upgrade to the SCX 6. Licence and software work in connection with the transition to the SCX 6.

  • Středočeské vodárny a kanalizace – Upgrade to the SCX 6, Czech Republic

    2012

    SVAK - upgrade to the SCX 6. Licence and software work in connection with the transition to the SCX 6 per customer participation.

  • OVAK Wastewater treatment plant Michálkovice – Upgrade to the SCX 6, Czech Republic

    2012

    WWTP Michálkovice, the Czech Republic - Upgrade to the SCX 6. Licence and software work in connection with the transition to the SCX 6.

  • Modernisation of water treatment plant Mostiště

    2012

    Delivery of following parts: low voltage, field instrumentation, process control, control room, radio data network.

  • Central WWTP Ostrava, Czech Republic

    2012

    Central Wastewater Treatment Plant: next phase of reconstruction - control system for the biological section.

  • Sliač Airport, the Ministry of Defence of the Slovak Republic, Slovakia

    2012

    The contract for NATO: reconstruction of the airport in Sliač. The construction of new loading from rail tankers including 2 km long pipeline to the reservoirs (3x250m3 ) and output into tank trucks.

  • Prague Airport, Czech Republic

    2012

    Prague Airport - measurement of density and pressure. Delivery of MicroMotions for measuring of density in the tank of fuel. Delivery of pressure gauges.

  • Pardubice Airport, Czech Republic

    2012

    Delivery of technology for storage, loading and unloading of products at the Airport of Pardubice, CZ. Delivery of automated control system and instrumentation - switchboard, field instrumentation and TAMAS system. Funded by the EU.

  • Ostrava Airport, Czech Republic

    2012

    Ostrava Airport - reconstruction of facilities. New wiring - cables, excavations - 22kV and 6kV for the airport area. Public lighting, gas connection. New (building + technology) high voltage substation HTS-2. New high voltage 22 and 6kV switchgear in three substations, new high voltage transformer, reconstruction of low voltage in substations.

  • ORDORIKO SE, Czech Republic

    2012

    Reconstruction of storage: Installation of two tanks (250 m3 ), installation of metering skids, build of new loading and unloading islands.

  • Neste Oil MUUGA, Estonia

    2012

    Design, production and recovery of 16 measuring skids and the system TAMAS for AC terminal. Skids based on volumetric measurement (PRIMA4) ACL. Colouring of the product by using devices EVA6. TAMAS system for unloading.

  • Modernisation of storage in Heřmanův Městec, Czech Republic

    2012

    Extensive modernization of fuel storage at two locations - Vrbice I and Vrbice II, it affects about 20 objects; realisation: 2010-2012. Construction work and new automated control system for the new technology, a new system of measurement and control + camera security system.

  • METROSTAV, Loukov depot, unit 237, Czech Republic

    2012

    Construction of warehouse storage capacity, supply of instrumentation for a new unit No 237.

  • LUKOIL NEFTOCHIM BURGAS, Bulgaria

    2012

    Railway terminal: Design, production and recovery of 11 measuring skids, TAMAS system for railway terminal (loading and unloading), mass measurement by Micromotions, Acculoads, integration to the LNHB system.

  • INKO, Loukov depot, unit PS 262, Czech Republic

    2012

    Following the delivery of METROSTAV: full supply for low voltage switchgear for unit PS 262 - construction electrical part. Delivery of the 10-fields switchboard.

  • Bahr Pump – TAMAS system and SKIDs for Eesti Energia, Estonia

    2012

    Delivery of 6 SKIDs for rail terminal, switchboard for automated control system and instrumentation. Software:TAMAS system. There were needed major adjustments for dispensing into rail tankers. Product is a fuel extracted from shale.

  • AGROPODNIK DOMAZLICE, Czech Republic

    2012

    Four old flowmeters were replaced by SMITH PRIME devices.

  • Additivation system for INA Rijeka and Solin, Croatia

    2012

    Additivation systems for dispensing into tank trucks at the terminal in INA Rijeka and Solin. The first use of the new blending unit Accuplus - 15pcs.

  • Skids for pipeline PETRONEEDS, Sudan

    2012

    Design and fabrication of filtration, measuring and regulating skids based on mass measurements at the beginning and at the end of the pipeline from the company STAROIL. Our first application of crude oil. Development and production of stationary Corioli Prover. The first use of the crude oil analyzer and auto sampler.

  • Measuring skids, KAR, Iraq

    2012

    Delivery of 26 measuring skids with Micromotion for the refinery in Erbil / Kurdistan. Corioli prover with triple mass flow measurement, FloBoss control.

  • VaS Žďár nad Sázavou – Upgrade to the SCX 6, Czech Republic

    2011

    VaS Žďár nad Sázavou - Upgrade to the SCX 6. Licence and software work in connection with the transition to the SCX 6.

  • VaS Boskovice – Upgrade to the SCX 6, Czech Republic

    2011

    VaS Boskovice - Upgrade to the SCX 6. Licence and software work in connection with the transition to the SCX 6.

  • Dracar CZ – Custody transfer measurement system on Skrochovice tankfarm

    2011

    Technology and control system for custody transfer measurement of unloading and loading and additive dosing of fuels on tax-free tankfarm.

  • Vapour recovery unit (VRU) for INSA Belozem loading terminal, Bulgaria

    2011

    Delivery and integration of vapour recovery unit with 150 m3 /h capacity.

  • Truck loading installation for Lukoil Ilientsi, Bulgaria

    2011

    Delivery of complete truck loading installation with 4 loading islands, 16 metering systems for light fuels, top and bottom loading, additive dosing system for Lukoil and Shell additives, blending of biofuels and coloring of diesel fuels. Installation is completely automated by TAMAS control system.

  • Reconstruction of Lukoil Bourgas Railway Terminal

    2011

    Delivery of containerized coloring system, system for measuring of loaded and unloaded products, and TAMAS supervising system.

  • Delivery of vapor recovery unit (cleaning of gasoline vapors) for Slovnaft, Slovakia

    2011

    Fabrication of 300 m3/h vapor recovery unit for truck loading terminal Bratislava, EPC Jordan Technologies.

  • Delivery of vapor recovery unit (cleaning of gasoline vapors) for MOL, Hungary

    2011

    Fabrication of 300 m3 /h vapor recovery unit for truck loading terminal Komárom, EPC Jordan Technologies.

  • Delivery of equipment for Neste Oil truck loading terminal in Tallinn-Muga, Estonia

    2011

    Engineering, fabrication, installation supervision and start-up of metering skids and control system. The facility is owned by Neste Oil, a Finnish oil refining and marketing company.

  • Delivery of equipment for Eesti Energia Narva truck loading facility, Estonia

    2011

    Delivery of metering skids, grounding equipment and TAMAS control system for truck loading terminal for gasoline and shell oil products. At the moment, the project is extended by railway terminal.

  • Filtering and metering system for Adbara depot, Sudan

    2011

    Skids 12" class 900 and 16" class 600 for filtration, pressure control and flow metering of diesel and gasoline in redundand design. Including intargation into existing SCADA system.

  • Delivery of vapour recovery unit for SINOPEC company, China

    2011

    Engineering, fabrication, installation and start-up of 400 m3 /h vapour recovery unit for Zhishan tankfarm.

  • Delivery of vapour recovery unit for CNOOC company, China

    2011

    Engineering, fabrication, installation and start-up of 400 m3/h vapour recovery unit for Yiwan - Shenzhen tankfarm.

  • Delivery of vapor recovery units (cleaning of gasoline vapors) for public gas stations, Italy

    2010

    2010-2011: Fabrication of 9 pcs of mini compact vapor recovery unit installed on gas stations, EPC Jordan Technologies.

  • Delivery of vapor recovery unit (cleaning of gasoline vapors) for JSC Okseta, Lithuania

    2010

    Fabrication of 150 m3 /h vapor recovery unit for truck loading terminal Kaunas, EPC Jordan.

  • Delivery of river tanker loading terminal for Slovenska plavba dunajska, Bratislava, Slovakia

    2010

    EPC delivery of loading facility for liquid chemicals to river rankers through loading arms DN200. Laoding arms are hydraulically actuated and equipped by ERS (Emergency Rrelease System).

  • Custody transfer measurement system on Ceska Lipa tankfarm

    2010

    Technology and control system for custody transfer measurement of unloading and loading and additive dosing of fuels on tax-free tankfarm. EPC contract.

  • Čepro, a.s. – Reconstruction of tank gauging system, Czech republic

    2010

    Integration of new tank gauging instruments into existing control system.

  • Čepro, a.s. – Reconstruction of pipeline pumping station – Czech republic

    2010

    Design, delivery installation of technology, electrical power supply and control system for pipeline pumping station Klobouky.

  • VaK Breclav – Dispatching centre VaK Breclav – Czech Republic

    2009

    Dispatching centre in Breclav CZ and other water supply sites

  • ZSSK CARGO – Transloading terminal in Čierna nad Tisou – Slovakia

    2009

    Complex supply of the engineering, technology and automation for railway transloading terminal for flamable products liquids.

  • Shell aviation fuel loading terminal in Helsinki, Finland

    2009

    Delivery of 8 grounding testers for tank truck loading.

  • Prague airport – Rehabilitation of aviation fuel handling system – Czech Republic

    2009

    Modernisation of technology for tank truck loading and installation of new automation system (EPC delivery).

  • NATO Roudnice – Tankfarm and terminal for diesel fuel, Czech Republic

    2009

    Delivery, fabrication, assembly and commissioning of complex technology part of tankfarm and tanktruck terminal including auxiliary operations.

  • Metering skids for Turkmenbashi complex of oil refineries, Turkmenistan

    2009

    Design, fabrication and start-up assistance. Measuring and control of amount of products when loaded into ships. There are 14 metering skids for custody transfer of different oil products. The skids have been installed in the sea terminal in the Turkmenbashi complex for measuring and control of amount of products when loaded into ships.

  • Vodovody a kanalizace Mladá Boleslav a.s. – TSLC and TSMGX stations – Czech republic

    2008

    Delivery of TSCL 422 and customized TSMGX stations.

  • Ostravské vodárny a kanalizace a.s. – TSX 24.3 stations – Czech republic

    2008

    Delivery of TSX 24.3 stations for the Waterworks and severage Ostrava.

  • State fuel reserves – Project documentation for State fuel reserves Bulgaria – Bulgaria

    2008

    BASIC DESIGN for 4 strategic fuel storages and terminals of the State fuel reserves of Bulgaria.

  • Paramo a.s. – Pardubice – Czech Republic

    2008

    Modification of tank truck loading terminal for loading of H-LBI (white spirit).

  • OKZ Holding – Delivery of equipment for the fuel tanks – Slovakia

    2008

    Delivery of electrical equipment for the fuel storage tanks.

  • FMC Technologies, Measurement Solutions, Hamburg – TanQuid fuel storage – Germany

    2008

    Delivery of additivation system EVA5 for truck fillings.

  • Čepro, a.s. – 3 fuel storages refurbishing – Czech republic

    2008

    Complex modernisation of the control system on tankfarms (EPC delivery).

  • Agropodnik Domažlice – Fuel storage Domažlice – Czech Republic

    2008

    Delivery of the trucks fuel loading technology including additives and biofuel blending.

  • Sinopec – technologies delivery – China

    2008

    Delivery of blending unit EVA 6, SKID service and bottom loading trucks technology.

  • Shanghai Pudong Airport, Additive dosing technology, China

    2008

    Design, engineering, delivery of additive dosing system. The referenced facility is located in Pudong airport, one of the biggest airports in the world. The fuel storage has been equipped with dosing system to manage increasing conductivity of Jet fuel. It is used for injection of additive agent into the product when unloaded from ships to the fuel storage at the airport. The EPC delivery included additive container with pumping skid and connection to current installation.

  • DALKIA a.s. – Heat generation plant, Trebovice – Czech Republic

    2007

    Complete reconstruction of Plant for Chemical Treatment of Water (Wonderware).

  • SKANSKA, a.s. – Fuel storage – Potěhy, Roudnice a Šlapánov – Czech Republic

    2007

    Refurbishment of fuel tanks and related work.

  • Real HM Nové Zámky – Fuel storage Nové Zámky – Slovakia

    2007

    A recuperation unit deployment.

  • LUKOIL Bulgaria – Tank truck loading terminal Plovdiv – Bulgaria

    2007

    Basic and Detail Design, engineering, EPC delivery on turn-key basis. The terminal has 4 loading bays for TOP and BOTTOM loading with capacity of 60 tank trucks loading per day.

  • FAU Přerov – Fuel storage Přerov – Czech Republic

    2007

    Expansion of tankfarm and tank truck loading terminal for biofuels blending. EPC delivery.

  • Chemoprojekt, a.s. – Roudnice storage – Czech Republic

    2007

    Delivery of automation control system and construction of storage tanks in Roudnice.

  • Čepro, a.s. – Terminal Roudnice nad Labem – Czech Republic

    2007

    TAMAS and SCADA SCX control systems for the fuel terminal.

  • Čepro, a.s. – Fuel storage Roudnice nad Labem – Czech Republic

    2007

    Fuel loading terminal refurbishing for Čepro.

  • Čepro, a.s. – Biofuels – Czech Republic

    2007

    Expansion of 11 tankfarms and tank truck loading terminals for biofuels blending. EPC delivery.

  • Army of the Czech Republic – Fuel storage Heřmanův Městec – Czech Republic

    2007

    Fuel tanks.

  • Additive dosing units – Poland

    2007

    Delivery of additive dosing units

  • Terminal Trebisov – Slovakia

    2006

    Vapour recovery and Additive dosing.

  • Glycol terminal BEGA Klaipeda – Lithuania

    2006

    Instrumantation and control system for ethylene glycol unloading from ships.

  • Cepro, a.s. – Terminal Sedlnice – Czech Republic

    2006

    TAMAS and SCADA SCX control systems for the fuel terminal.

  • Čepro, a.s. – Fuel storage Roudnice nad Labem – Czech Republic

    2006

    Implementation of automation system for the Roudnice fuel storage.

  • Čepro a.s. – Sedlnice terminal – Czech Republic

    2006

    Construction of new tankfarm for petroleum products with capacity 100 000m3 (EPC delivery)

  • Sinopec – Terminal Ningbo – China

    2006

    Design, delivery and engineering of additive dosing system EVA6, additive pump station and loading arms on taktruck terminal.

  • Retize – SCADA system – Bulgaria

    2005

    SCADA system for a hydraulic power plant cascade control

  • Bobov Dol – Technology for sulphuric acid loading – Bulgaria

    2005

    Delivery of design and technology for sulphuric acid loading

  • VHOS, a.s. – Water supply dispatching Svitavy – Czech Republic

    2005

    Regional water supply dispatching Svitavy.

  • KP RIA Brno – Waste water treatment plant Boskovice – Czech Republic

    2005

    Automatized control system at the waste water treatment plant Boskovice.

  • KP RIA Brno – Waste water treatment plant Blansko – Czech Republic

    2005

    Electrical part, IC, and automatized control system at the waste water treatment plant Blansko

  • Hydrobiel – Sewerage dispatching Glogowek – Poland

    2005

    Sewerage dispatcher system Glogowek

  • Interagua – Water supply dispatching Guayaquil – Ecuador

    2005

    Water supply and sewage control system in Guayaquil - Ecuador (2,5 mil inhab.). Guayaquil is major ecuadorian trade and transport centre. In 2005 was installed approx. 20 remote telemetry units and installed radio data network and central control room based on system SCADA SCX.
    The system is under permanent development. In 2010 is in following state: connected approx. 70 objects, using 2 servers (in different locations) in hot-standby mode, communication over radio data network and GPRS, integration of 3rd party systems (PLC controllers, datalogers).

  • Varna – Fuel warehouse – Bulgaria

    2005

    Conceptual design for the fuel warehouse re-construction in Varna

  • UAB „Okseta“ – Kedainiai – Terminal Vilnius – Lithuania

    2005

    TAMAS and SCADA SCX control systems for the fuel terminal.

  • UAB „Lukoil Baltija“ – Mazeikiai – Terminal Kedainiai – Lithuania

    2005

    TAMAS and SCADA SCX control systems for the fuel terminal

  • SIA „Lukoil Baltija R“ – Riga – Terminal Olaine – Latvia

    2005

    TAMAS and SCADA SCX control systems for the fuel terminal.

  • Paramo, a.s. – Paramo Pardubice Terminal – Czech Republic

    2005

    Fuel dispensing terminal, including painting and additive feeding technologies. Major delivery.

  • Orlen/FMC Smith Meter – Additive dosing units EVA – Poland

    2005

    Delivery of additive dosing units.

  • Mesaideed – QAPCO – Qatar Petrochemical Company – Qatar

    2005

    Delivery of an earthing equipment for a Client in Qatar

  • WiK Opole – The first waterworks project in Opole – Poland

    2004

    The first project - realization of 3 water supply sites

  • VaS Znojmo – Local Water Treatment Plant in Znojmo – Czech Republic

    2004

    Reconstruction of local Water Treatment Plant control system in Znojmo CZ.

  • Rejnok VaS – Waste water treatment plant in Krizanov – Czech Republic

    2004

    Reconstruction of control system in waste water treatment plant in Krizanov CZ

  • Progress Trading, s.r.o. – Fuel terminal and warehouse – Slovak republic

    2004

    Complex delivery of warehouse and filling tray technology for a fuel terminal (railway loading station, tanks, filling trays, additive feeding technologies).

  • ORLEN, S.A., Tankfarm – Poland

    2004

    Delivery of additive dosing system EVA5 for jet fuel for military purposes.

  • VHOS Moravska Trebova – Waste water treatment plant in Jevicko – Czech Republic

    2003

    Reconstruction of control system in waste water treatment plant in Jevicko.

  • VHOS Moravska Trebova – Regional water supply dispatching in Moravska Trebova – Czech Republic

    2003

    Reconstruction of control system, regional water supply dispatching - next phase.

  • VaK JC – South Bohemia – Dispatching in Ceske Budejovice – Czech Republic

    2003

    Regional water supply dispatching in Ceske Budejovice, South Bohemia, CZ - next phase.

  • ORLEN, S.A., Tankfarm Mostiska – Warszawa – Poland

    2003

    Delivery of additive dosing system EVA5.

  • Mazeikiu Nafta – Terminal, Butinge – Lithuania

    2003

    Project and delivery of MaR (Measurement and Regulation) for two new oil tanks.

  • KFOR – Kosovo terminal – Yugoslavia

    2003

    Dispensing terminal at an army airport, Pristina.

  • Czech Army – Warehouse, Hermanuv Mestec – Czech Republic

    2003

    Project and delivery of a light fuel additive feeding unit.

  • AVE MATROX UAB – Terminal, Kaunas – Lithuania

    2003

    Control, technology, fuel dispensing unit.

  • Policka town – Waste water treatment plant in Policka – Czech Republic

    2002

    Reconstruction of control system in waste water treatment plant in Policka CZ

  • Bourgas Voda – Water supply dispatching centre – Bulgaria

    2002

    Regional water supply dispatching centre with 30 stations.

  • CEPRO a.s. – Terminal Klobouky – Czech Republic

    2002

    Reconstruction of a fuel warehouse and dispensing station.

  • Sofijska voda – Water supply dispatching centre

    2001

    Regional water supply dispatching centre with 40 stations.

  • CEPRO a.s. – Terminal Mstetice – Czech Republic

    2001

    Complete warehouse reconstruction.

  • Vodovody a kanalizace Kladno Melnik a.s. – VaK Kladno Melnik – Czech Republic

    2000

    Local system of Water Treatment Plan control, Vrapice.

  • VHOS Moravska Trebova a.s. – Water supply dispatching centre, Policka – Czech Republic

    2000

    Regional water supply dispatching centre with 12 sites.

  • VaK JC – South Bohemia water supply dispatching centre – Czech Republic

    2000

    Regional water supply dispatching centre - 300 water supply sites.

  • Jihocesky vodarensky svaz- Ceske Budejovice a.s. – Dispatching centre JVS – Czech Republic

    2000

    South Bohemia country dispatching centre + water supply sites (approx.40).

  • PTI Technologijos UAB – Terminal – Litva

    2000

    TAMAS® and automation system SCADA SCX for fuel terminal.

  • TROLEX CZ s.r.o. – Monitoring – Czech Republic

    1999

    Monitoring of a power system for OKD.

  • Vodovody a kanalizace Kladno Melnik a.s. – Water treatment plant, Klicava – Czech Republic

    1999

    Local Water Treatment Plan system control, Klicava.

  • Vodovody a kanalizace Kladno Melnik a.s. – Water supply dispatching – Czech Republic

    1999

    Regional water supply dispatching centre, visualisation with SAIA stations.

  • Ostravske vodovody a kanalizace a.s. – Water treatment plant – Czech Republic

    1999

    Local system of Water Treatment Plan, Nova Ves and Water Treatment Plan Dubi control.

  • CEPRO a.s. – Terminal Cerekvice nad Bystrici – Czech Republic

    1999

    Delivery of MaR (Measurement and Regulation) and computer-assisted control system for a construction of new fuel terminal tanks.

  • IVO POWER / Teplarny Olomouc a.s. – Monitoring system – Czech Republic

    1998

    Monitoring of a coal storage yard for CO.

  • Vodovody a kanalizace Uherske Hradiste a.s. – Water supply dispatching – Czech Republic

    1998

    Regional water supply dispatching centre of 70 sites.

  • Vodovody a kanalizace Ricany u Prahy a.s. – Water supply dispatching – Czech Republic

    1998

    Regional water supply dispatching centre servicing 5 water supply sites.

  • Vodovody a kanalizace Prerov a.s. – Water supply dispatching – Czech Republic

    1998

    Regional water supply dispatching, Hranice, Prerov - total of 60 sites.

  • Vodovody a kanalizace Kromeriz a.s. – Water supply dispatching – Czech Republic

    1998

    Regional water supply dispatching centre of 30 sites. Computer-assisted control system and wiring Water Treatment Plan, Kromeriz.

  • VHOS a.s. Moravska Trebova – Water supply dispatching – Czech Republic

    1998

    Regional water supply dispatching with 15 water supply sites.

  • PARAMO Pardubice a.s. – Railway terminal – Czech Republic

    1998

    Light fuel oil and oil filling into railway tanks including feeding of additives.

  • OMV Slovakia a.s. – Fuel warehouse, Komarno – Slovak Republic

    1998

    Project, complex delivery of technology and control of a river fuel warehouse on the Danube with loading into railway wagon tanks and truck tanks.

  • CEPRO a.s. – Terminal, Smyslov u Tabora – Czech Republic

    1998

    Delivery of facilities, technology, MaR (Measurement and Regulation) and computer-assisted control system of fuel terminal.

  • CEPRO a.s. – Terminal, Slapanov u Havlickova Brodu – Czech Republic

    1998

    Delivery of facilities, technology, MaR (Measurement and Regulation) and computer-assisted control system of a fuel terminal.

  • VaK Prerov a.s. – Water Treatment Plant – Czech Republic

    1997

    Computer-assisted control system project, delivery of computer-assisted control system of a water treatment plant Prerov - Troubky.

  • Ostravske vodovody a kanalizace a.s. – Water supply dispatching – Czech Republic

    1997

    Central control system of a water supply dispatching centre Ostrava with 100 water supply sites.

  • VSZ Doprava a.s. – Fuel Terminal, Kosice – Slovakia

    1997

    Engineering, project and delivery of fuel terminal technology at a locomotive depot.

  • Shell Czech Republic a.s. – Light fuel warehouse, Ostrava – Czech Republic

    1997

    Engineering, project and delivery of a fuel terminal technology and control.

  • OMV Slovakia a.s. – Fuel Warehouse, Klacany – Slovak Republic

    1997

    Project, complete delivery of warehouse technology and control.

  • Ceska sprava letist a.s. / ESSO Czech a.s. – Airport fuel warehouse, Ruzyne – Czech Republic

    1997

    Engineering, project and delivery of wiring, MaR (Measurement and Regulation) and computer-assisted control system of fuel terminal.

  • CEPRO a.s. – Terminal Tremosna u Plzne – Czech Republic

    1997

    Delivery of project, wiring, MaR (Measurement and Regulation) and computer-assisted control system of a recovery unit and fuel product line terminal.

  • MCHZ Ostrava a.s. – Terminal – Czech Republic

    1996

    Delivery of amine terminal filling technologies.

  • Vodovody a kanalizace Prostejov a.s. – Water supply dispatching and Water Treatment Plan – Czech Republic

    1996

    Control system, MaR (Measurement and Regulation) and Wiring Water Treatment Plan Prostejov - Hrdiborice, regional water supply control system.

  • Vodovody a kanalizace Mlada Boleslav a.s – Water supply dispatching – Czech Republic

    1996

    Regional water supply dispatching of 80 sites.

  • Vodovody a kanalizace Hodonin a.s. – Water supply dispatching and Water Treatment Plan – Czech Republic

    1996

    Regional control system of 45 water supply site.

  • Slovak Army – Fuel Warehouse, Zemianske Kostolany – Slovak Republic

    1996

    Engineering, project and delivery of a fuel warehouse reconstruction (oil management).

  • Shell Czech Republic a.s. – Airport Warehouse of Light Fuels, Brno – Czech Republic

    1996

    Delivery of complex technology and control of light fuel terminal.

  • CEPRO a.s. – Fuel Terminal, Strelice u Brna – Czech Republic

    1996

    Delivery of a project, wiring, technology and control of reconstructed and new filling trays of a fuel terminal (railway loading station, tank station, filling trays, vapour return line).

  • CEPRO a.s. – Fuel Terminal, Hnevice – Czech Republic

    1996

    Delivery of recovery, technology and control units for new filling trays.

  • AGA GAS s.r.o. – Recovery control – Czech Republic

    1996

    Project and delivery of electric equipment and computer-assisted control system of a petrol vapor recovery line for PARAMO Pardubice a.s. railway terminal.

  • ABB Lummus Chemoprojekt Brno – Chemopetrol Litvinov Engineering – Czech Republic

    1996

    Participation in a project involving re-instrumentation of an ethylene unit.

  • Teplarny Otrokovice a.s. – Control system of a heat generation plant – Czech Republic

    1995

    Control system of an ash pipeline system.

  • OKD – Koksovna Ostrava – Control system of a coking plant – Czech Republic

    1995

    Project and delivery of MaR (Measurement and Regulation) and pressure control in assemblies of coking batteries.

  • Mine CSM a.s. – Control system of a heat generation plant – Czech Republic

    1995

    Control and dispatching system of a heat generation plant built in three stages as per the reconstruction of the individual boilers including monitoring and evaluation of in-plant energy distribution.

  • Vodovody a kanalizace Boskovice a.s. – Water supply dispatching centre – Czech Republic

    1995

    Regional control system of water supply sites.

  • Chemis s.r.o. – Fuels Terminal, Slavkov u Brna – Czech Republic

    1995

    Project and delivery of fuel terminal technology (railway loading station, tank station, filling trays, vapour return line).

  • CEPRO a.s. – Fuels Terminal Cerekvice n. Bystrici – Czech Republic

    1995

    Delivery of Wiring, MaR (Measurement and Regulation) and computer-assisted control system of a fuel terminal.

  • Benol s.r.o. – Fuel terminal, Bzenec – Czech Republic

    1995

    Delivery of Wiring, MaR (Measurement and Regulation) and computer-assisted control system.

  • Teplarny Karvina a.s. – Monitoring – Czech Republic

    1994

    Monitoring, heat generation and power consumption control at a heat generation plant.

  • Vodovody a kanalizace Breclav a.s. – Water supply dispatching centre – Czech Republic

    1994
  • Vodarny a kanalizace – Zdar nad Sazavou a.s. – Czech Republic

    1994

    Water supply dispatching centre - regional control system of 54 water supply sites.

  • SKODAexport a.s. – Product line supervision – India

    1994

    Technical supervision over an installation of a SCADA system for a construction of a product line at Kandla-Bhatinda, India.

  • KAME s.r.o – Fuels Warehouse in Prerov – Czech Republic

    1994

    Engineering, project and delivery of fuel terminal technology (railway loading station, tank station, filling trays, vapor return line) in Prerov.

  • Various customers – Assembly of fuel filling station – Czech Republic

    1993

    Delivery and assembly of technology and wiring for 12 fuel filling stations.